Activity Uncrashing Heuristic with Noncritical Activity Rescheduling Method for the Discrete Time-Cost Trade-Off Problem

No Thumbnail Available

Date

2020

Journal Title

Journal ISSN

Volume Title

Publisher

Asce-amer Soc Civil Engineers

Research Projects

Organizational Units

Organizational Unit
Civil Engineering
(2000)
The Atılım University Department of Civil Engineering was founded in 2000 as a pioneer for the Departments of Civil Engineering among the foundation schools of Ankara. It offers education in English. The Department of Civil Engineering has an academic staff qualified in all areas of the education offered. In addition to a high level of academic learning that benefits from learning opportunities through practice at its seven laboratories, the Department also offers a Cooperative Education program conducted in cooperation with renowned organizations in the construction sector. Accredited by MÜDEK (Association of Evaluation and Accreditation of Engineering Programs) (in 2018), our Department has been granted the longest period of accreditation to ever achieve through the association (six years). The accreditation is recognized by ENAEE (European Network for Accreditation of Engineering Education), and other international accreditation boards.

Journal Issue

Abstract

Despite intensive research efforts that have been devoted to discrete time-cost optimization of construction projects, the current methods have very limited capabilities for solving the problem for real-life-sized projects. This study presents a new activity uncrashing heuristic with noncritical activity rescheduling method to narrow the gap between the research and practice for time-cost optimization. The uncrashing heuristic searches for new solutions by uncrashing the critical activities with the highest cost-slope. This novel feature of the proposed heuristic enables identification and elimination of the dominated solutions during the search procedure. Hence, the heuristic can determine new high-quality solutions based on the nondominated solutions. Furthermore, the proposed noncritical activity rescheduling method of the heuristic decreases the amount of scheduling calculations, and high-quality solutions are achieved within a short CPU time. Results of the computational experiments reveal that the new heuristic outperforms state-of-the-art methods significantly for large-scale single-objective cost minimization and Pareto front optimization problems. Hence, the primary contribution of the paper is a new heuristic method that can successfully achieve high-quality solutions for large-scale discrete time-cost optimization problems.

Description

Atan, Tankut/0000-0002-3241-4617; Sonmez, Rifat/0000-0001-6163-3264; Aminbakhsh, Saman/0000-0002-4389-1910

Keywords

Scheduling, Optimization, Algorithms, Multiple objective analysis, Project management